PREPARATION OF BQ n T-OFF
1.6-PREPARATION OF BILL OF QUANTITIES AND TAKING OFF SHEETA bill of quantities is a document which lists all the items necessary for the complete construction of works. Each item includes a description and a quantity. When a contractor is asked to prepare a tender he is supplied with all the contract documents. Another reason for including BOQ/BQ (Bill of Quantities) in contract documents is that it provides the engineer with the opportunity of seeing how the contractors have arrived to their estimate.
1.6.1-Taking Off Sheet/Dimension Sheet
a) First Stage - Taking Off
Taking off - to calculate the quantity in each item of work. the taking off sheet, which is sometimes called a dimension sheet, is ruled in the following way; column A, column B, Column C and Column D, appear twice on each sheet.
Taking off - to calculate the quantity in each item of work. the taking off sheet, which is sometimes called a dimension sheet, is ruled in the following way; column A, column B, Column C and Column D, appear twice on each sheet.
It consists of transferring the description and quantity the description and quantity from the taking-off sheet to the abstract sheet (as shown in Appendix A2) and collecting together items, which can be, billed under one item. If the quantity has to be converted from one unit to another unit this is done on the abstract sheet. c) Third stage - Writing a bill of quantities There are certain principles, which should always be followed when writing a bill of quantities. It should be concise, accurate and well written (as shown in Appendix A3). i) Descriptions Each item should be described in enough detail to enable anyone reading the bill of quantities to be able to locate the item in the works. |
ii)Order Items should be entered in a logical order. It is suggested that the following order be used.
iii) Accuracy It is usually necessary to re-measure civil engineering works when they are completed to determine the exact value of the work, and therefore it is not necessary to calculate the quantities too accurately when preparing the bill. iv) Numbering All items should be measured consecutively page by page. v) Abbreviations The following abbreviations are often used on the dimension sheets:
|
1.6.2 Preparation of Bill of Quantities
The example of a bill of quantities for a river works contract for a new power station might contain the following ;
- Section A - list of principal quantities
- Section B - Preamble
- Section C - Day work schedule
- Section D - Work items
- Section E - Grand Summary
List of Section D-Work item:-
- Part 1 - General Items
- Part 2 - Demolition and site works
- Part 3 - Access roads
- Part 4 - Pipe work
- Part 5 - Dredging
- Part 6 - Pump chambers
- Part 7 - Circulating water ducts
- Part 8 - Wharf wall
- Part 9 - Jetty
Section A - List of Principal Quantities
The list of principal quantities being the main components of the works, with their approximate estimated quantities, so that tenderers obtain an overall picture of the general scale and character of the proposed works at the outset.
A list of principal quantities relaying to a reservoir as follows :-Part 1 | General Items Provisional Sums Prime Cost items | RM20,000 RM76,000 |
Part 2 | Reservoir Excavation Concrete Formwork Steel reinforcement | 1500 m3 12500 m3 6600 m2 150 tonnes |
Part 3 | Pipe work Pipelines Valves | 850 m 22 no. |
Part 4 | Embankment Filling | 12000m3 |
Part 5 | Access Road Concrete road slab | 1800 m3 |
Part 6 | Fencing Mild steel fence | 1400 m |
Section B - Preamble The preamble in a civil engineering bill of quantities is to indicate to tendering contractors whether methods measurement other than the CESMM have been used for any part of works and whether any modification have been made in applying the CESMM to meet special needs where there are important practical reasons for adopting a different procedure. Section C - Daywork Schedule It is necessary to make provision for a daywork evaluation of work which cannot be assessed at bill rates. The CESMM provides three alternatives procedures.
|
Section D - Work Items
Section E - Grand Summary (total costs for the sections) |
1.6.3 - The general formula for quantities
No comments:
Post a Comment